Friday, November 22, 2013

Closed In


The house is now all closed in and ready for winter (just in time too, since Monday is supposed to be so cold)!  This week the insulation was put in and the garage doors were installed.  I am starting to get really excited about living there but Rick has yet to tell me it will be before March…. I think he doesn't want me bugging him, ha!

Oh, and the siding continues to move along….probably only 1-2 more days before it is done.


Door in the garage




Burying propane tank

I thought I picked out a color that matches the trim, looks like I missed.

Sunday, November 17, 2013

Bonus!


Saturday work is always a wonderful little bonus to the week….


Friday, November 15, 2013

Another week completed

This week:
Heat and air roughed in

Front sidewalk poured

Steps built in the garage
More siding on
  



Friday, November 8, 2013

Siding and Sidewalks

In the fireplace :)
The exterior of the house is really starting to take shape.  The windows arrived!  Were the correct size!  And were installed!!  Hooray!  All of the exterior doors were also installed this week and the siding and trim work has begun.  We also made decisions on the perfect curve for the front walkway and they did the prep work to pour that next week.






Saturday, November 2, 2013

Wired for sound

We have ended week eight of building.  The roughed in plumbing and electric have passed inspection.  I finally found a paint store that could correctly mix paint to match the house color.  Then Ted dug out a little from around the base of the house and he and I painted the cinder blocks.  We finished yesterday between rain drops.  I am so glad to have it painted before the siding gets put on next week!

A few other little accomplishments this week….  Propane tank was dropped off for burying, the well was finished and connected to the house, and the electric company came and plotted out running the electric to the house….  Next week should be busy with the windows and exterior doors being installed, then the siding can be put on and the heat and air guys can start!

Living Room (office on the right side)

Dining Room and Foyer

Kitchen

Master Room closets and bathroom

Friday, October 25, 2013

Love that dirty water...

The end of this week (only 7 weeks since we broke ground) saw more electric and plumbing run inside the house.  I actually made decisions on switch, outlet and light locations and I think it is turning out well!  The county came and put in the culvert for the driveway.  And then today our well was dug.  The boys (and I) were fascinated by the water gushing out of the top of the well.  It was very dirty water pouring out from under ground and Zach looked at me at one point and said, "We have to drink that?!?"





And, both of the older boys got to drive the skid steer.





Wednesday, October 23, 2013

Centered to window? or Centered to room?....AGH...I don't know!!


Today, I was asked a hundred questions relating to light locations, switch locations, outlet locations, faucet types, cubby sizes, bathroom vanity types.....  I am pretty opinionated and definitely want a say in all of it, but the problem I am having is that I need more time to wrap my head around all the options and come up with something I can live with!!  It is fun, but today was a little overwhelming as I made rapid decisions, one after another, meanwhile praying that I don't make any major mistakes.



As you can see by the pictures, the electricians and plumber have arrived and have drilled holes in everything!!  


Linds, can you tell the off centeredness I was talking about??


The showers and bathtubs arrived this week....


The windows arrived and were suppose to be installed, but the window company sent the wrong size for the majority of the windows and now we have to wait until next week for the correct ones to be sent.

The chimney was framed in today!

And, the mason completed all but the top pavers for my beautiful front steps!!





Thursday, October 17, 2013

Roof....check

See all my window openings?!?
It's too early in this project to refer to it as 'plodding along'....so I will refrain for now.  Instead I will share with you that the roofers have finished putting on the shingles, the window openings are all cut out and now ready for the actual window, my downstairs family closet is framed and the access spaces in the attic and garage have sub flooring.  All super exciting steps forward.



Wednesday, October 16, 2013

Cease Raining

Since the rain finally stopped this past
Monday we have been moving forward
again.  The past 2 days have added
shingles over the main part of the
house and a little over half of the garage.
I now have stairs to the attic, prep work
for the windows has been done (they
should be delivered this Friday), a front
porch roof has been completed and I have
the start of an electric box and meter in
the garage.  The daily visual differences
are starting to slow down....


Window wrapping


Big house....little Marcus



Wednesday, October 9, 2013

That's a wrap


This morning, there was a flurry of activity at the house!  In the span of three hours, the roofers had tar paper on all of the roofs, and the framers plus Rick and Ted had the house-wrap up.  It's amazing how much gets done with a mere 6 days of rain forecasted....I am guessing that we will be standing still for a little while.

Dormer windows


This week, with rain threatening for the first time since we started, the framers have finished the roof and my dormer!  (In case you were wondering the dormer window will be bigger than what is currently cut out.)




These are the bricks for the front steps.


Look at this great contractor we have!
He even sweeps out the garage at the end of the day!!